Every task from accepting an application to handing over the keys — in the right order

Landlord Handbook
Updated 1 July 2026
England & Wales
Annual Access

Use This Timeline for Every New Tenancy

Missing a step — especially around deposit protection, document service or right to rent checks — can have serious legal consequences. Work through this timeline in order and tick off each task as it is completed.

Stage 1: Application Accepted (Days 1–3)

  • Confirm acceptance to the applicant in writing
  • Collect holding deposit (maximum 1 week's rent)
  • Issue written receipt for holding deposit
  • Set the deadline for agreement (15 days from holding deposit, unless extended in writing)
  • Instruct referencing agency or begin own checks

Stage 2: Referencing (Days 1–14)

  • Carry out right to rent checks for all adult occupants — mandatory before tenancy starts
  • Obtain employer reference (or accountant reference for self-employed)
  • Obtain previous landlord reference
  • Obtain credit check
  • Assess guarantor application if required (obtain guarantor references and credit check)
  • Retain copies of all right to rent documents

Stage 3: Agreement and Documents (Days 7–21)

  • Prepare tenancy agreement — use a Renters Rights Act-compliant template
  • Confirm all compliance certificates are current (GSC, EICR, EPC)
  • Obtain any missing or expired certificates before proceeding
  • Prepare deposit prescribed information
  • Prepare required written tenancy information — for tenancies from 1 May 2026, prescribed information about key terms must be provided before the tenancy is signed or otherwise agreed; may be included in the tenancy agreement or provided separately
  • Prepare inventory — inspect the property and take dated photographs
  • Prepare welcome pack and emergency contacts sheet
  • Prepare move-in checklist

Stage 4: Pre-Move-In (Days 14–28)

  • Send tenancy agreement to tenant(s) for review
  • Confirm move-in date and time
  • Confirm payment method for first month's rent and deposit
  • Arrange standing order for ongoing rent payments
  • Cut keys — one set per tenant plus one spare
  • Carry out final property check and clean
  • Complete property ready checklist

Stage 5: Move-In Day

  • Collect first month's rent (cleared funds)
  • Collect deposit (cleared funds)
  • Deduct holding deposit from first payment
  • Sign tenancy agreement — all parties
  • Serve all required documents: Gas Safety Certificate, EPC, EICR, and required written tenancy information (if not already provided before signing)
  • Serve deposit prescribed information (or note 30-day deadline)
  • Complete and sign inventory — both parties
  • Record meter readings — gas, electricity, water
  • Hand over keys and obtain signed key receipt
  • Test smoke alarms in tenant's presence
  • Test CO alarm in tenant's presence (where present)
  • Show tenant stopcock and fuse box locations
  • Provide appliance instruction manuals
  • Provide welcome pack and emergency contacts sheet
  • Complete and retain move-in checklist

Stage 6: First 30 Days

  • Protect deposit in a government-approved scheme within 30 days
  • Serve deposit prescribed information within 30 days (if not done on move-in day)
  • Notify gas supplier of new occupant and meter reading
  • Notify electricity supplier of new occupant and meter reading
  • Notify water supplier of new occupant and meter reading
  • Notify council tax office of new tenancy
  • Confirm standing order is set up and first payment received
  • Diarise first inspection (6–8 weeks from move-in)
  • Diarise compliance renewal dates

Key Deadlines Summary

  • Right to rent checks: must be completed before tenancy starts
  • Deposit protection: within 30 days of receipt
  • Deposit prescribed information: within 30 days of receipt
  • Required written tenancy information: must be provided before the tenancy is signed or otherwise agreed (for tenancies from 1 May 2026)
  • Gas Safety Certificate: must be served before occupation
  • EICR: must be served before occupation
  • EPC: must be available before marketing

Related Resources

Disclaimer

Guidance only. Landlord Handbook provides practical information to help landlords understand their responsibilities. It is not legal or financial advice. Always check the latest GOV.UK guidance and seek professional advice where appropriate.

Landlord Handbook
Expert UK Landlord Guidance
www.landlordhandbook.co.uk
© 2026 Landlord Handbook. All rights reserved.
This document is the intellectual property of Landlord Handbook. Reproduction for commercial purposes is prohibited without written consent.